Home » PMI » PMI-001 » Which of the following describes the input to the direct and manage project execution that is used to bring the project back in line and is the part of feedback loop?
Which of the following describes the input to the direct and manage project execution that is used to bring the project back in line and is the part of feedback loop?
A. Corrective action
B. Performance reports
C. Workarounds
D. WBS updates
E. Performance update
Correct Answer: A
Explanation/Reference: