Which of the following statements are true regarding the critical path of a project schedule?

Which of the following statements are true regarding the critical path of a project schedule?
A. Any project activity with a float time of zero or greater is considered a critical path tasks
B. Any project activity with a positive float time is considered a critical path tasks
C. None of the statements are true
D. Any project activity with a float time that equals zero is considered a critical path tasks

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.