Who should be primary person responsible for deciding whether the changes to the project charter are necessary?

You are the project manager at a large investment bank. Your current project involves developing a creative financing solution for a large bio-tech company in order to facilitate the acquisition of another company. Specifically, your project involves issuing convertible debt securities in order to access a new pool of low-cost capital. This transaction is the largest ever convertible transaction in the bio-tech company. Unfortunately, your project is plagued by frequent changes to project charter. Who should be primary person responsible for deciding whether the changes to the project charter are necessary?
A. Project manager
B. Change control board
C. Project team
D. Project sponsor
E. Stakeholders