You are in the process of directing the performance of a planned project activities and managing various technical and organizational interfaces that exist within your project. All of the following are required inputs EXCEPT:
A. Work performance information
B. Project management plan
C. Approved change requests, approved defect repair
D. Approved corrective actions, approved preventive actions
E. Validated defect repair, administrative closure procedure