Which of the following best describes why one would use a resource histogram versus a responsibility assignment matrix?
A. Unlike the responsibility assignment matrix, a resource histogram shows when people will do their jobs
B. Unlike the responsibility assignment matrix, a resource histogram shows the reporting relationships of project team members
C. Unlike the responsibility assignment matrix, a resource histogram is helpful in tracking project costs and can be aligned with the organization’s accounting systems
D. Unlike the responsibility assignment matrix, a resource histogram describes the inert-dependencies among project activities.