Which of the following statements are TRUE regarding the scope verification statement?
A . Scope verification involves evaluating overall project performance to ensure that the project will satisfy specified project requirements
B . None of the statements are true
C . Scope verification is primarily concerned with verifying the correctness of work results
D . The tool/ technique of scope verification is inspection