Which of the following is the portion of the approved cost estimate that has been budgeted for an activity during a certain time period?

With respect to value analysis which of the following is the portion of the approved cost estimate that has been budgeted for an activity during a certain time period?
A. Planned value (PV)
B. Earned value (EV)
C. Actual cost (AC)
D. Cost variance (CV)