Which of the following best describes a cost and schedule planning techniques where details are developed for the near term and general allocations are made for work far in the future.

Which of the following best describes a cost and schedule planning techniques where details are developed for the near term and general allocations are made for work far in the future. Detail is developed for work far in the future as information becomes available to do so.
A. Milestone lists
B. Planning components
C. Schedule network templates
D. Rolling wave planning
E. Decomposition