Home » PMI » PMI-001 » Which of the following process takes the activities that are defined in the WBS and activity list, and accesses the amount of time required to complete these activities?
Which of the following process takes the activities that are defined in the WBS and activity list, and accesses the amount of time required to complete these activities?
A. Activity duration estimation
B. Activity definition
C. Activity sequencing
D. Schedule development
Correct Answer: A
Explanation/Reference:
Download Printable PDF. VALID exam to help you PASS.
|
|