You are in the process project a project schedule for repainted your house, you first need to scrap off the existing paint, and then add a layer of primer. The primer provides the paint a better bonding surface so it sticks to the base material much better. Without priming, drywall surfaces will soak up more finish paint in some areas than in others, producing a splotchy effect.
You decided to speed up the process by starting priming before all the scraping is finished. To correctly sequence these activities, which of the following should you do?
A. Add float time between the priming and painting tasks
B. Fast track the priming and painting tasks
C. Ad lag time to the priming task
D. Add lead time to the priming task