Which of the following statements are false regarding project time management?
A. Schedule development involves estimating type and qualities of resources required to perform each schedule activity
B. Activity definition involves identifying schedule activities that are required to meet project deliverables
C. Schedule control involving changes to project schedule
D. None of the choices are correct
E. Activity sequencing involves identifying dependencies among schedule activities