Which of the following is the LEAST helpful input?

You are in the process of developing an approximation of the costs of resources needed to complete each schedule activity. Which of the following is the LEAST helpful input?
WBS, WBS dictionary
A. Market place conditions, commercial databases
B. Cost estimation policies/ templates, historical information,
C. project team knowledge
Activity cost estimates, activity cost estimate supporting details
D. Schedule management plan, staffing management plan, risk
E. register