Which of the following are not true regarding decision tree analysis?

With respect to risk management, which of the following are not true regarding decision tree analysis?
A. Solving decision tree indicates which decision yields the greatest expected value to the decision maker
B. Decision tree are tool of quantitative risk analysis process
C. The PDM schedule is typically used to construct the decision tree
D. Decision tree shows the impact of one decision over another