You are using three point estimating technique to estimate the estimate of a scheduled activity. Which of the following statement are true given the following data:
Pessimistic= 100 days
Optimistic= 40 days
Most likely= 65 days
Average =66.6 days
A. The calculations were performed assuming a exponential distribution
B. Not enough information is provided
C. The calculations were performed assuming a triangular distribution
D. The calculations were performed assuming a beta distribution
E. The calculations were performed assuming a UNIFOREM distribution