Which of the following statements is true regarding PDM (precedence diagramming techniques)?

Which of the following statements is true regarding PDM (precedence diagramming techniques)?
A. PDM often uses the start-to-start relationship
B. PDM often uses the finish-to-start relationship
C. PDM often uses the finish-to-finish relationship
D. PDM often uses the start-to-finish relationship