What is the SPI of this project?

You are the project manager for the company that sells online music. Your project is to develop a new content management system that will not only manage all users purchases and downloads, but will automatically learn the users music interests in order to make future product recommendations. In addition your content management system must scale to support millions of concurrent music downloads a day.
Your team has made significant progress on the project. You are preparing the performance of a project to date and have calculated the following measurements.
PV=4,000 EV= 3,500 AC= 3,000
What is the SPI of this project?
A. 1.333
B. 0.875
C. 1.14
D. 1.16
E. 0.75