You are in the process of estimating the type of and quantity of resources needed to complete individual schedule activities. All of the following are tools/ techniques you can use in this process EXCEPT:
A. Parametric estimating
B. Published estimating data, project management software
C. Alternatives analysis
D. Bottom-up estimating
E. Expert judgment