Which of the following documents initiates a project and authorizes the project manager to assign organizational resources to the project?

Which of the following documents initiates a project and authorizes the project manager to assign organizational resources to the project?
A. RFQ document
B. Work breakdown structure
C. Project plan
D. RFB document
E. Project charter