You are project manager responsible for constructing a new sports arena for the upcoming Olympics. Construction began on a project over a year ago. The stakeholders of the project want a status report on the performance of the project to date. You’ve obtained the following measurements: BAC=500, ETC=200, PV=500, AC=200, EV=300, CPI=1.5 Based on the measurements above, which of the following statements are TRUE?
A. The cost performance of the project is better than expected
B. The schedule performance of the project is worse than expected
C. The schedule performance of the project is better than expected
D. The cost performance of the project is worse than expected