According to the PMI which of the following is considered as a special case of contract closure?
A. Contract fraud
B. Contract default
C. Contractual non performance
D. Early termination of contract
E. Contract bankruptcy
According to the PMI which of the following is considered as a special case of contract closure?
A. Contract fraud
B. Contract default
C. Contractual non performance
D. Early termination of contract
E. Contract bankruptcy