Which of the following processes in the initial process group is one responsible for producing a high-level definition of the project and documenting the project requirements, deliverables and method of acceptance?

In which of the following processes in the initial process group is one responsible for producing a high-level definition of the project and documenting the project requirements, deliverables and method of acceptance?
A. Scope planning
B. Develop preliminary project scope statement
C. Develop project management plan
D. Develop project charter
E. Create WBS

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.