Project cost control includes all of the following EXCEPT:
A. Identifying various costing alternatives
B. Monitoring cost performance to detect variances from cost baseline
C. Ensuring requested changes are agreed upon
D. Bringing expected cost overruns within acceptable limits
E. Informing stakeholders of approved changes