Which of the following is the BEST candidate for a three-point estimate?

Which of the following is the BEST candidate for a three-point estimate?
A . A schedule activity with a considerable variation B . A brief schedule activity that takes a couple of hours C . A schedule activity with a fixed duration
D . A schedule activity with little duration variation