You are in the process of developing an approximation of the costs of the resources needed to complete each schedule activity. All of the following are tools/ techniques you can use in this process EXCEPT:
A. Determine resource cost rate
B. Cost aggregation
C. Analogous estimation, bottom-up estimation, parametric estimation
D. Cost of quality, project management software
E. Vendor bid analysis, reserve analysis