You are in the process of developing an approximation of the costs of the resources needed to complete each schedule activity.

You are in the process of developing an approximation of the costs of the resources needed to complete each schedule activity. All of the following are tools/ techniques you can use in this process EXCEPT:
A. Determine resource cost rate
B. Cost aggregation
C. Analogous estimation, bottom-up estimation, parametric estimation
D. Cost of quality, project management software
E. Vendor bid analysis, reserve analysis