Which of the following inputs is least helpful?

Your company manufactures memory chips for workstation computer. Your project involves manufacturing a very high capacity memory chip. 128GB.
You have worked on he same project two year ago to manufacture low capacity memory chip.2GB.
You are in the DEVELOP THE PROJECT CHARTER process. Which of the following inputs is least helpful?
A. Organizational process assets, standardized guidelines and performance measurement criteria’s
B. Historical information on the previous project manufacturing 2GB capacity chip. This information could be helpful since this new project is similar in nature.
C. Enterprise environmental factors, such as stakeholders risk tolerances and marketplace condition
D. The project constraints and assumptions to make sure that the any significant project risk can be identified and mitigated
E. The project’s preliminary scope statement that document the characteristic of the project

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.