Which of the following statements are not true regarding corrective actions?
A. Corrective actions are input to various controlling process
B. Corrective action is used to bring expected future project performance in line with the project plan
C. Approved corrective actions are inputs to the direct and manage project execution project
D. Corrective actions are the outputs of processes in the controlling process group