Quantitative risk analysis involves all of the following except:

Quantitative risk analysis involves all of the following except:
A. Identify feasible cost and schedule targets given project risks
B. Ensure that risk management policies are being followed
C. Assess probability of meeting project objectives
D. Quantify the potential project outcomes and probabilities