Which duration estimation technique did u just see?

You’ve been hired as a project manager for a local community college. The community college wants you upgrade the hardware for each of its web servers, and install the necessary security patches for each web- server.
You are ready to begin the activity duration estimation process. You are told that there are total 50 web-servers that need to be upgraded. From past experience, you know that it takes about two hours to upgrade the hardware and install patches on each web server. Therefore, you estimate that it will take approximately 100 hours to complete this project. Which duration estimation technique did u just see?
A. Analogous estimation
B. Quantitatively based durations
C. Decomposition
D. Expert judgment
E. Reserve time

Download Printable PDF. VALID exam to help you PASS.