You are the chief technology officer of a major stock exchange in United States. You have just been provided a preliminary project scope statement from your project sponsor with regards to reengineering the organization’s back office accounting, billing and administrative system. Which of the following the BEST NEXT plan of action?
A. Start documenting the impact of the requested changes
B. Start establishing and managing project communication channels
C. Start establishing management plans
D. Start scope verification
E. Start performing activities to accomplish project objectives