What should you do?

You are currently working on a web development project to develop a new user-interface for a legacy mainframe banking application. You are under a Times and Material contract to develop a wed based interface for this application. You have finished the work 20 hours earlier than expected. This means that the profit of your company will decrease. What should you do?
A. You should tell the customer you’ll be adding additional requirements to the project in order to meet profit estimates.
B. You should add activities to the project to increase the number of billable hours.
C. You should inform the customer that your project is complete
D. You should invoice the customer for the expected billable amount, as allowed by the provisions of your contract.