Which of the following is the BEST plan of action?

You have been assigned to a project to build a large 30-story condominium in Las Vegas. The condominium will feature luxurious amenities like state of the art work-out facilities, conference centers, valet services, maid services, spas, gourmet dining and resort style pools.
You’ve calculated the estimated project completion date. However, the estimated completion date is 2 months after the desired completion date. After analyzing the project network diagram, you’ve determined that many of the activities have discretionary dependencies. To decrease the project duration, you’ve requested additional resources but were told that NO additional resources are available for your project. Assuming that the project has low risks, which of the following is the BEST plan of action?
A. Reduce the quality of deliverables
B. Omit risk management activities
C. Omit a project activity
D. Perform schedule activities in parallel
E. Crash the schedule

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.