Which of the following statements are FALSE regarding project scope management plan?
A. Project scope management plan specifies how changes to the project scope statement will be managed.
B. Project scope management plan specifies how WBS will be created, maintained and approved
C. The project scope management plan describes how the project scope will be defined and managed by the project scope management team
D. The project scope management plan is an output of the Scope Definition process
E. The project scope management plan is contained within the project management plan