You are the project manager in the I.T. department of a major hospital. Your current project involves developing a web-based interface for legacy mainframe patient-tracking application. Your current project has recently experienced a change where many of the agreed-upon WBS elements were modified as a result. Which type of change has occurred within your project?
A. Project change
B. Quality change
C. Scope change
D. Schedule change
E. WBS update