Which of the following is the MOST likely candidate for a three-point estimate?

Which of the following is the MOST likely candidate for a three-point estimate?
A. A schedule activity with a fixed duration
B. A schedule activity with a considerable variation
C. A well-understand schedule activity with little expected variation
D. A brief schedule activity that takes a couple of hours