Which of the following statements are false?

You are in process of defining how to plan and execute the risk management activities for your project. Which of the following statements are false?
The output of this process is risk management plan
A. The inputs to this process includes the project scope statement,
B. project management plan, and the risk register The tools/ techniques of this process are planning meetings and
C. analysis
None of the choices are correct
D.