Which of the following are true regarding the critical path EXCEPT:

Which of the following are true regarding the critical path EXCEPT:
A. Critical path activities that are delayed can result in a negative float
B. A critical path can run over a dummy activity
C. Changes to the end date of the project may not require a change to the project network
D. None of the choices are correct
E. A project can have multiple critical paths

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.