Which of the following statements are true regarding the SPI (schedule performance index) measurement?
A. A SPI greater than one indicates that schedule performance is better than expected
B. A negative SPI indicates that schedule performance is better than expected
C. A SPI less than one indicates that schedule performance is better than expected
D. A positive SPI indicates that schedule performance is better than expected