Your project is nearing completion when a previously undocumented risk is identified. The risk could negatively affect the outcome of the project. Which of the following is the BEST action to perform next?
A. Create a workaround
B. Develop a risk response plan to mitigate the risk
C. Add reserves to the project to adjust for the risks
D. Notify the management team about the impact of the risk
E. Analyze the risk