Which of the following statements are FALSE:

You are the project manager at a company developing an online music store. You are in the process of calculating the cost budget for this project using a combination of parametric estimation and bottom-up estimation. Which of the following statements are FALSE:
A. The cost baseline is considered the expected cost of the project
B. Projects may have multiple cost baselines to measure different aspects of cost performance
C. The cost baseline is an output of the Cost Estimating process
D. The cost baseline is used to measure project performance and variances