Which of the following statements are true?

You have been recently assigned to provide an accurate project schedule for a large construction company.
Your lead engineer has given you the following estimates for several critical path activities. Your stakeholders want you to commit to a completion date for these critical path activities. Which of the following statements are true?


There is approx. 68 percent chance that the project will complete
A. between 64 days and 78 days.
There is approx. 95 percent chance that the project will complete
B. between 64 days and 78 days.
There is approx. 68 percent chance that the project will complete
C. between 57 days and 85 days.
There is approx. 99 percent chance that the project will complete
D. between 64 days and 78 days.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.