Which of the following is best to perform next?

During project executing, a previously unidentified risk has just occurred. This risk will negatively effect the outcome of the project. Which of the following is best to perform next?
A. Alert the management team
B. Develop the contingency plan
C. Add reserves to the project to adjust for the risk
D. Perform the risk audit
E. Create a work around