Which of the following statements about fast-tracking is TRUE?

Which of the following statements about fast-tracking is TRUE?
A. Fast tracking refers to assigning additional resources to a project in an attempt to decrease project schedule/ timeline
B. Fast tracking is the process of increasing the schedule by overlapping various project tasks
C. One of the advantages of fast-tracking is that it can often lead to reduced rework and reduces project risks
D. None of the statements are true
E. Fast tracking involves performing activities sequentially