Which of the following is the LEAST helpful INPUT?

You are in the process of establishing a total cost baseline for measuring project performance. Which of the following is the LEAST helpful INPUT?
A. WBS, WBS dictionary
B. Project funding requirements, performance reports
C. Activity cost estimates & supporting details
D. Contract, resource calendars, cost management plan
E. Project scope statement, project schedule