Your project team is already created the WBS, developed estimates for the work packages, and sequenced the project activities using the precedence diagramming method. Which action should be performed NEXT?
A. Finalize the project schedule
B. Implement schedule change control system
C. Apply schedule compression techniques
D. Obtain acceptance of completed project scope
E. Decompose the work packages into smaller components called schedule activities