Which of the following statements are FALSE?

Which of the following statements are FALSE?
A. Funding limit aggregation is used to ensure that the expenditure of funds is reconciled with the funding limits imposed by the performing organization
B. Cost aggregation and parametric estimation is a tool/ technique of cost budgeting process
C. Analogous estimating is a form of expert judgment and is generally less accurate than other techniques, but is also less costly
D. Parametric estimating is an estimating technique using project characteristics/ parameters to estimate the total project costs