Which of the following statements are FALSE regarding the CPM method?

Which of the following statements are FALSE regarding the CPM method?
A. The latest start of the task can be determined by subtracting the duration of the task from the latest finish date of task
B. The forward pass is used to calculate the early finish dates and early start dates for the uncompleted portions of all network activities
C. Free slack is the amount of time one can delay the start of a particular task, without delaying the completion of the project.
D. The backward pass is used to calculate the late finish dates and late start dates for the uncompleted portions of all network activities