You are the project manager assigned to construct a new 10-story office building. You are trying to estimate the costs for this project. You start by assigning the costs associated with each of the project activity. Then you sum up all the individual costs into a final cost estimate. Which type of cost estimation technique did you use?
A. Analogous estimation
B. Parametric estimation
C. Monte Carlo methods
D. Bottom-up estimation