Which of the following objectives is LEAST likely accomplish by implementing a project-wide application of the configuration management system?
A. Provides a mechanism to communicate changes to stakeholders
B. Provides opportunities to improve the project by considering the impact of each change
C. Provides a method to identify and manage risks