You are using the three points estimating techniques to estimate the duration of the scheduled activities. Which of the following statements are true given the following data?
Pessimistic=200 days
Optimistic days=100 days
Most likely=120 days
Average=140 days
Variance=466.66
A. The calculations were perform assuming a uniform distribution
B. Not enough information is provided
C. The calculation were performed assuming a exponential distribution
D. The calculation were performed assuming a triangular distribution
E. The calculations were performed assuming he beta distribution