Which of the following statements are true given the following data?

You are using the three points estimating techniques to estimate the duration of the scheduled activities. Which of the following statements are true given the following data?
Pessimistic=200 days
Optimistic days=100 days
Most likely=120 days
Average=140 days
Variance=466.66
A. The calculations were perform assuming a uniform distribution
B. Not enough information is provided
C. The calculation were performed assuming a exponential distribution
D. The calculation were performed assuming a triangular distribution
E. The calculations were performed assuming he beta distribution