All of the statements regarding control accounts and planning packages are true EXCEPT:

All of the statements regarding control accounts and planning packages are true EXCEPT:
A. Planning packages reflect a future segment of work within a control account that has not yet been decomposed into detailed work packages
B. A control account is an assigned WBS level used to monitor cost and schedule performance of significant element of work
C. As work becomes more clearly defined, planning packages are converted into work packages
D. Each work package / planning package may be associated with only one control account
E. Control accounts and planning packages are tools / techniques of activity definition process